Macarthur Water Filtration Plant upgrade

Tank base in preparation

Tank base in preparation

Tank base in preparation

Pipe laying

2020 saw the Macarthur Water Filtration Plant upgrade project come to a close; despite the many challenges faced due to COVID-19.

The upgrade was conducted on a brownfield site (meaning the site had to remain operational at all times). The team faced COVID-19 restrictions and endured

volatile weather conditions, install and water quality challenges along the way.